Petro Canada - Edmonton Refinery
August 2005

HOT PIPE COATING ®
An exchanger end was running at 258° F ( 126° C ) before being insulated with HOT PIPE COATING ®. Petro Canada's objective was to reduce operating temperature to 120° F (49° C). HOT PIPE COATING ® was applied at approximately 250 mils / ¼" DFT (Dry Film Thickness), reducing operating temperature to 100° F (38 ° C), which exceeded expectations.

 HOT PIPE COATING - Petro Canada HOT PIPE COATING - Petro Canada

The recommended coating system consists of:
Prime coat: HOT PIPE COATING ® - 250 mils / ¼" DFT ( Dry Film Thickness )
Base coat: SUPERTHERM ® - 10 mils DFT
Top coat: ENAMO GRIP WB ® - 3 mils DFT

HOT PIPE COATING - Petro Canada HOT PIPE COATING - Petro Canada

Project pictures and report courtesy of Lee Reeves - Energy Conservation Coordinator